EVANS LIBRARY PHASE 3 RENOVATION UPDATE

Engineering, Design and Construction Services Project Manager Dennis Gray, AIA, has been working diligently on the Evans Library renovation project called Re-Imagine. The project consists of three phases and Dennis is happy to report that phase 3 is well under way. Construction for phase 3 began in January 2017 and will be complete in December 2017. The project consists of renovation of the service areas on the first floor in the Annex and the service desk in the Evans library building. Additionally, the project includes a complete renovation of the Annex fourth floor and most of Evans second floor. These are all public and student study spaces including new classrooms and flexible study areas with raised access flooring incorporating floor outlets for electrical and data. The photos depict the newly renovated service desks in both buildings. The approximate square footage of renovations is 72,000SF.
Thanks so much to Dennis and his team for their work on Re-Imagine!